Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? 11ea19f5_238d_351d_ab61_b333bbd6f7a1_TB5361_00 October 5, 2022 by 8i9x6 The early finish for A increases to 31. The early start time for A increases to 24. The early finish time for B increases to 31. The early start time for D falls to 23. See Answer The early finish time for B increases to 31.