Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B? 11ea19f5_238d_351d_ab61_b333bbd6f7a1_TB5361_00

The early finish time for B increases to 31.